Beginning April 12, areas of the Main Pavilion fourth floor will be closed for renovations. These renovations are part one of a six-phase project that includes the fourth and fifth floors of the Main Pavilion. We will communicate the progress as this project advances.
Phase one schedule is as follows:
- April 12 – 414 will be closed for renovations
- April 26 – 409 through 418 and the connecting corridor between Main and 4 Brazos
As a reminder, the Main Pavilion Imaging X-ray room is also under construction. All outpatient X-rays will be directed to Sweetwater Pavilion.